WBS of Bullet train

PROJECT:  BULLENT TRAIN  FROM MUMBAI TO AHMEDABAD
490 KM
SNO ACTIVITIES TIME IMMEDIATE
    IN DAYS PREDECESSORS
       
1 TO IDENTIFY THE SUITABLE TECHNOLOGY 150 NONE
  AVAILABLE IN THE WORLD    
       
2 TO ENTER INTO MOU WITH AGENCY 150 1
  FOR TECHNOLOGY TRASFER     
       
3 TO SURVEY THE ROUTE 200 2
       
4 BUDGET PREPATION 120 3
       
5 BUDGET ALLOCATION 60 4
       
6 SORTING OUT LAND RELATED ISSUES, IF ANY 200 5
       
7 RECRUITMENT OF PERSONNEL 150 2
       
8 CONSTRUCTION OF FACTORY 800 5
       
9 DEVELOPMENT OF TRAIN 700 7
       
10 LAYING OF TRACKS & ELECTRIFICATION 700 6
       
11 TEST RUN 60 10
       
    3290