Drawing Activity on Arrow Diagram and Use of Dummy Activities
This video draws an activity-on-arrow (A-O-A) diagram for a given work breakdown structure of a project with explanation of steps. It also discusses about use of dummy activities. Watch the video and try drawing the A-O-A diagram for given WBS on your own.
The below WBS is for your exercise:
The below WBS is for your exercise:
Activities
|
Immediate Predecessors
|
Activity Time in Days
|
|
|
|
A
|
None
|
10
|
B
|
None
|
12
|
C
|
None
|
18
|
D
|
A
|
15
|
E
|
B
|
20
|
F
|
C
|
25
|
G
|
D, E
|
15
|
H
|
D, E
|
18
|
I
|
E
|
8
|
J
|
E
|
9
|
K
|
J
|
7
|
L
|
F
|
10
|
M
|
K, L
|
12
|
N
|
I
|
5
|
O
|
G
|
22
|
P
|
H, N
|
21
|