Friday, February 13, 2015

Probabilistic Situation

This video takes a probabilistic problem, draws network diagram, finds critical path and discusses the effect of time on probability of completion of the project (with calculation of probabilities).


Wednesday, February 11, 2015

Drawing Activity on Arrow Diagram and Use of Dummy Activities

This video draws an activity-on-arrow (A-O-A) diagram for a given work breakdown structure of a project with explanation of steps. It also discusses about use of dummy activities. Watch the video and try drawing the A-O-A diagram for given WBS on your own.



The below WBS is for your exercise:

Activities
Immediate Predecessors
Activity Time in Days



A
None
10
B
None
12
C
None
18
D
A
15
E
B
20
F
C
25
G
D, E
15
H
D, E
18
I
E
8
J
E
9
K
J
7
L
F
10
M
K, L
12
N
I
5
O
G
22
P
H, N
21

Monday, February 9, 2015

Work Breakdown Structure (WBS)

This video explains the concept of WBS by taking a simple example of project. Watch it and apply similar thinking by taking any other small project of your choice.